2023/24 Asset Management Outturn

Meeting: 29/05/2024 - Cabinet (Item 15)

15 Asset Management Outturn 2023/24 pdf icon PDF 128 KB

Finance and Resources

To report the actual expenditure against budget for the Asset Management Plan in 2023/24 and to update the Asset Management Plan requirement for 2024/25.

Additional documents:

Decision:

Resolved:

1.  That the expenditure for the year on Asset Management projects, as shown in Annex 1, be noted.

2.  That the updated budget for Asset Management projects in 2024/25, as shown in Annex 2, be approved.

 

Minutes:

Consideration was given to a report of the Finance and Resources Portfolio Holder which compared the actual expenditure on Asset Management Plan (AMP) projects with the approved budget for 2023/24.

 

The total revised AMP budget in 2023/24 was £3.560M. Actual expenditure in the year was £1.875M. The outturn position for 2023/24 had been reviewed, following which the AMP requirement for 2024/25 had been updated.

 

Having considered the options and for the reasons set out in the report, the recommendations were proposed by Councillor Flood, seconded by Councillor P North and Cabinet agreed to the following:

Resolved:

1.  That the expenditure for the year on Asset Management projects, as shown in Annex 1, be noted.

2.  That the updated budget for Asset Management projects in 2024/25, as shown in Annex 2, be approved.