APPLICATION NO.

19/00876/FULLS

 

APPLICATION TYPE

FULL APPLICATION - SOUTH

 

REGISTERED

17.06.2019

 

APPLICANT

Mr and Mrs Shutler

 

SITE

Glebe Farm, Rectory Hill, West Dean, SP5 1JL,  WEST TYTHERLEY AND FRENCHMOOR

 

PROPOSAL

Erection of dwelling and garage with annex, following the removal of existing agricultural buildings

 

AMENDMENTS

Amended/Additional information received 16/12/19 & 13/01/20

 

CASE OFFICER

Mr Paul Goodman

 

 

 

Delegate to Head of Planning & Building for completion of legal agreement to secure;

  • Secure the offsetting land to ensure the scheme is nitrate neutral in perpetuity.
  • Future management of the offsetting land, and
  • New Forest SPA contribution.

Then PERMISSION subject to:

 

1.

The development hereby permitted shall be begun within three years from the date of this permission.

Reason:  To comply with the provision of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

 

2.

No development shall take place above DPC level of the development hereby permitted until samples and details of the materials to be used in the construction of all external surfaces hereby permitted have been submitted to and approved in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved details.

Reason:  To ensure the development has a satisfactory external appearance in the interest of visual amenities in accordance with Test Valley Borough Revised Local Plan (2016) Policy E1.

 

3.

The development hereby approved shall be undertaken in full accordance with the provisions set out within the Tree Survey, Arboricultural Impact Assessment, Arboricultural Method Statement & Tree Protection Plan (Haydens, Proj. No 7811, 11/12/2019).

Reason:  To ensure the enhancement of the development by the retention of existing trees and natural features during the construction phase in accordance with Test Valley Borough Revised Local Plan policy E2.

 

4.

Tree protective measures installed (in accordance with the tree protection condition) shall be maintained and retained for the full duration of works or until such time as agreed in writing with the Local Planning Authority. No activities, nor material storage, nor placement of site huts or other equipment what-so-ever shall take place within the barrier.

Reason:  To ensure the avoidance of damage to existing trees and natural features during the construction phase in accordance with Test Valley Borough Revised Local Plan policy E2.

 

 

5.

All service routes, drain runs, soakaways or excavations in connection with the development hereby permitted shall remain wholly outside the tree protective barrier.

Reason:  To ensure the avoidance of damage to existing trees and natural features during the construction phase in accordance with Test Valley Borough Revised Local Plan policy E2.

 

6.

No development shall take place above DPC level until full details of hard and soft landscape works have been submitted and approved. Details shall include-where appropriate: proposed finished levels or contours; means of enclosure; car parking layouts; other vehicle and pedestrian access and circulation areas; hard surfacing materials. Soft landscape works shall include: planting plans; written specifications (including cultivation and other operations associated with plant and grass establishment); schedules of plants, noting species, plant sizes and proposed numbers/densities. The soft landscape proposals shall include details of soft boundary treatments to the outside edges of the site. Notwithstanding the submitted information suitable soft landscape proposals should be native species chosen to provide screening whilst retaining an informal character in the rural area.  The landscape works shall be carried out in accordance with the implementation programme and in accordance with the management plan.

Reason:  To improve the appearance of the site and enhance the character of the development in the interest of visual amenity and contribute to the character of the local area in accordance with Test Valley Borough Revised Local Plan (2016) Policy E1 and E2.

 

7.

The development shall not be occupied until space has been laid out and provided for the parking and manoeuvring of vehicles to enable them to enter and leave the site in a forward gear in accordance with the approved plan and this space shall thereafter be reserved for such purposes at all times.

Reason:  In the interests of highway safety in accordance with Test Valley Borough Revised Local Plan (2016) Policy T1.

 

8.

Any gates shall be set back at least 4.5 metres from the edge of the carriageway of the adjoining highway.

Reason:  In the interest of highway safety in accordance with Test Valley Borough Revised Local Plan (2016) Policy T1.

 

9.

Details of any external lighting shall be submitted to and approved in writing by the local planning authority prior to first installing any such lighting before the building(s) is/are occupied.  Development shall be carried out in accordance with the approved details.

Reason:  To safeguard the amenities of the area and/or in the interests of road safety in accordance with Test Valley Borough Revised Local Plan (2016) Policy E8.

 

10.

The development hereby approved shall be designed and built to meet Regulation 36 2 (b) requirement of 110 litres/person/day water efficiency set out in part G2 of Building Regulations 2015.

Reason:  In the interests of improving water usage efficiency in accordance with policy E7 of the Test Valley Borough Revised Local Plan 2016.

 

11.

There shall be no construction or demolition works, no machinery shall be operated, no processes carried out and no deliveries received or dispatched outside the following times: 07:30 to 18:00 hours Monday to Friday and 08:00 to 13:00 hours on Saturday.  In addition, no such activities shall take place on Sundays, Bank or Public holidays.

Reason:  In the interests of the amenities of neighbouring properties in accordance with Test Valley Borough Local Plan policies E8 and LWH4.

 

12.

In the event that contamination is found at any time during demolition and/or construction works, the presence of such contamination shall be reported in writing to the Local Planning Authority without delay and development shall be suspended on the affected part of the site until a remediation scheme for dealing with that contamination has been approved by the Local Planning Authority.  The approved remediation scheme shall be implemented and, if requested, a verification report, for the purpose of certifying adherence to the approved remediation scheme, shall be submitted to the Local Planning Authority prior to the site being brought in to use.

Reason:  To ensure a safe living/working environment in accordance with Test Valley Borough Local Plan 2006 policy HAZ04.

 

13.

Development shall proceed in accordance with the measures set out in Sections 3.5 to 3.10 of the Preliminary Ecological Appraisal Report by Practical Ecology Ltd (November 2019).  

Reason:  To ensure the protection of protected/notable species in accordance with Policy E5 of the Test Valley Revised Local Plan DPD.

 

14.

Prior to the first occupation of the dwelling hereby permitted the existing structures/buildings relating to the previous permitted development notifications (15/01677/PDQS, 15/00168/PDMB and 14/01947/PDMBS), the unauthorised replacement structure and any mobile home shall be demolished and removed from the site.

Reason:  In order ensure no net increase in residential dwellings in the countryside in accordance with policy COM2 of the Test Valley Borough Revised Local Plan 2016 and to ensure that the resulting development has a satisfactory external appearance in the interest of visual amenities in accordance with Test Valley Borough Revised Local Plan (2016) Policies E1 and E2.

 

15.

The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers:

7880-D-LAP

7811-D-AIA

g109/103p

121/103P

Reason:  For the avoidance of doubt and in the interests of proper planning.

 

 

 

Notes to applicant:

 

1.

The development hereby permitted shall be carried out and completed strictly in accordance with the submitted plans, specifications and written particulars for which permission is hereby granted or which are subsequently submitted to, and approved in writing by, the Local Planning Authority and in compliance with any conditions imposed by the Local Planning Authority.

 

2.

In reaching this decision Test Valley Borough Council (TVBC) has had regard to the National Planning Policy Framework and takes a positive and proactive approach to development proposals focused on solutions. TVBC work with applicants and their agents in a positive and proactive manner offering a pre-application advice service and updating applicants/agents of issues that may arise in dealing with the application and where possible suggesting solutions.

 

Supporting documents: