APPLICATION NO.
|
19/01615/FULLS
|
|
|
APPLICATION TYPE
|
FULL APPLICATION -
SOUTH
|
|
|
REGISTERED
|
28.06.2019
|
|
|
APPLICANT
|
Mr Robert Tylor
|
|
|
SITE
|
Martins , Horsebridge Road, Houghton, SO20 6LY,
HOUGHTON
|
|
|
PROPOSAL
|
Two storey extension, garage
conversation erection of new garage; construction of detached
dwelling including package treatment plant
|
|
|
AMENDMENTS
|
Amended Plans 28.08.19,
23.04.20 & 26.06.20
|
|
|
CASE
OFFICER
|
Mr Paul Goodman
|
|
|
|
|
|
PERMISSION subject to:
|
|
1.
|
The
development hereby permitted shall be begun within three years from
the date of this permission.
Reason: To comply with the provision
of Section 91 of the Town and Country Planning Act 1990 as amended
by Section 51 of the Planning and Compulsory Purchase Act
2004.
|
|
2.
|
No
development shall take place above DPC level of the development
hereby permitted until samples and details of the materials to be
used in the construction of all external surfaces hereby permitted
have been submitted to and approved in writing by the Local
Planning Authority. Development shall be carried out in accordance
with the approved details.
Reason: To ensure the development
has a satisfactory external appearance in the interest of visual
amenities in accordance with Test Valley Borough Revised Local Plan
(2016) Policy E1.
|
|
3.
|
No development
shall take place above DPC level of the development hereby
permitted until details for the protection of all hedgerows, during
the construction phase of the development, within the site has been
submitted to and approved in writing by the Local Planning
Authority. Once approved, the development hereby approved shall be
undertaken in full accordance with the approved details and the
provisions set out within the Arboricultural Impact Assessment /Method Statement
ref D1829AIAb (Alderwood 31st July
2019), and its accompanying Tree Protection Plan.
Reason: To ensure the enhancement of
the development by the retention of existing trees and natural
features during the construction phase in accordance with Test
Valley Borough Revised Local Plan policy E1, E2 &
E9.
|
|
4.
|
Tree
protective measures installed (in accordance with the tree
protection condition) shall be maintained and retained for the full
duration of works or until such time as agreed in writing with the
Local Planning Authority. No activities, nor material storage, nor
placement of site huts or other equipment what-so-ever shall take
place within the barrier.
Reason: To ensure the avoidance of
damage to existing trees and natural features during the
construction phase in accordance with Test Valley Borough Revised
Local Plan policy E2.
|
|
5.
|
All
service routes, drain runs, soakaways or excavations in connection
with the development hereby permitted shall remain wholly outside
the tree protective barrier.
Reason: To ensure the avoidance of
damage to existing trees and natural features during the
construction phase in accordance with Test Valley Borough Revised
Local Plan policy E2.
|
|
6.
|
No
development shall take place above DPC level until full details of
hard and soft landscape works have been submitted and approved.
Details shall include-where appropriate: proposed finished levels
or contours; means of enclosure; car parking layouts; other vehicle
and pedestrian access and circulation areas; hard surfacing
materials; minor artefacts and structures. Soft landscape works
shall include: planting plans; written specifications (including
cultivation and other operations associated with plant and grass
establishment); schedules of plants, noting species, plant sizes
and proposed numbers/densities. The soft landscape proposals shall
include details of soft boundary treatments to the outside edges of
the site. The landscape works shall be
carried out in accordance with the implementation programme and in
accordance with the management plan.
Reason: To improve the appearance of
the site and enhance the character of the development in the
interest of visual amenity and contribute to the character of the
local area in accordance with Test Valley Borough Revised Local
Plan (2016) Policy E1 and E2.
|
|
7.
|
The
development shall not be occupied until space has been laid out and
provided for the parking and manoeuvring of vehicles to enable them
to enter and leave the site in a forward gear in accordance with
the approved plan and this space shall thereafter be reserved for
such purposes at all times.
Reason: In the interests of highway
safety in accordance with Test Valley Borough Revised Local Plan
(2016) Policy T1.
|
|
|
8.
|
Any
gates shall be set back at least 4.5 metres from the edge of the
carriageway of the adjoining highway.
Reason: In the interest of highway
safety in accordance with Test Valley Borough Revised Local Plan
(2016) Policy T1.
|
|
|
9.
|
The
development hereby approved shall be designed and built to meet
Regulation 36 2 (b) requirement of 110 litres/person/day water
efficiency set out in part G2 of Building Regulations
2015.
Reason: In the interests of
improving water usage efficiency in accordance with policy E7 of
the Test Valley Borough Revised Local Plan 2016.
|
|
|
10.
|
The
development hereby permitted shall not be carried out except in
complete accordance with the details shown on the submitted plans,
numbers:
617.PL.211 Rev A
617.PL.BLOCK Rev A
617.PL.SITE Rev C
617.SU.001
617.SU.002
617.SU.003
617.SU.004
617.SU.005
617.SU.006
617.PL.001 Rev C
617.PL.002
617.PL.003 Rev B
617.PL.004 Rev B
617.PL.005 Rev A
617.PL.006 Rev B
617.PL.007 Rev B
617.PL.201 Rev B
617.PL.202 Rev B
617.PL.203 Rev A
617.PL.204 Rev A
617.PL.205 Rev B
617.PL.206 Rev B
617.PL.207 Rev A
617.PL.208 Rev B
617.PL.209 Rev B
617.PL.210 Rev A
Reason: For the avoidance of doubt
and in the interests of proper planning.
|
|
|
11.
|
The
development of the new dwelling hereby permitted shall not be
commenced until the ‘Bio-bubble’ treatment plant has
been installed to service both the existing and proposed dwelling.
The treatment plant shall be retained and maintained in accordance
with the Bio-bubble Maintenance and Management System (LA
Hally Architect, 5th August
2020) unless otherwise agreed in writing by the local planning
authority.
Reason: In order to avoid adverse
impact on the Solent and Southampton Water SPA by way of additional
nitrates emanating from the development in accordance with the
Conservation of Habitats and Species Regulations 2017 and Test
Valley Borough Revised Local Plan 2016 Policy LE5.
|
|
|
12.
|
Prior
to the commencement of development the access shall be constructed
with the visibility splays of 2.4m by 37.4m (North) and 2.4m by
36.5m (South) in accordance with Plan 6371/202 and maintained as
such at all times. Within these visibility splays notwithstanding
the provisions of the Town & Country Planning (General
Permitted Development) Order 2015 (or any Order revoking and
re-enacting that Order) no obstacles, including walls, fences and
vegetation, shall exceed the height of 1 metres above the level of
the existing carriageway at any time.
Reason: In the interest of highway
safety in accordance with Test Valley Borough Revised Local Plan
(2016) Policy T1.
|
|
|
13.
|
No
works pursuant to the development hereby permitted shall be
undertaken outside of 08.00-18.00 hours Monday to Friday and
08.00-13.00hours on Saturdays or at any time on
Sundays, Public and Bank
Holidays.
Reason: To maintain the character
and amenities of the surrounding local area in accordance with Test
Valley Borough Local Plan 2016 policies LHW4 and E8.
|
|
|
14.
|
Notwithstanding the provisions of the Town and Country Planning
(General Permitted Development) Order 2015 (or any order revoking
and re-enacting that Order with or without modification), no
fences, gates, walls or other means of enclosure shall be erected
within the curtilage of any dwelling house.
Reason: In order that the Local
Planning Authority can exercise control in the locality in the
interest of the visual amenity of the area and the character and
appearance of the conservation are in accordance with Test Valley
Borough Revised Local Plan (2016) Policies E1, E2 and
E9.
|
|
|
15.
|
No development shall take place
above DPC level of the development hereby permitted until a
schedule of hedgerow management and maintenance for a minimum
period of 5 years has been submitted to
and approved in writing by the Local Planning Authority. The
management plan shall include long term design objectives,
management responsibilities and maintenance schedules for all
existing hedgerows within and surrounding the site. The hedgerow
shall be maintained in accordance with the approved
schedule. Any part of the
hedgerow or that is removed, dies or becomes, in the opinion of the
Local Planning Authority, seriously damaged or defective within
this period, shall be replaced before the end of the current or
first available planting season following the failure, removal or
damage of the planting.
Reason: To
enable the development to
respect, complement and positively integrate into the character of
the area in accordance with Test Valley Borough
Revised Local Plan (2016) Policies E1, E2 & E9.
|
|
|
Notes
to applicant:
|
|
|
1.
|
The
development hereby permitted shall be carried out and completed
strictly in accordance with the submitted plans, specifications and
written particulars for which permission is hereby granted or which
are subsequently submitted to, and approved in writing by, the
Local Planning Authority and in compliance with any conditions
imposed by the Local Planning Authority.
|
|
|
2.
|
In
reaching this decision Test Valley Borough Council (TVBC) has had
regard to the National Planning Policy Framework and takes a
positive and proactive approach to development proposals focused on
solutions. TVBC work with applicants and their agents in a positive
and proactive manner offering a pre-application advice service and
updating applicants/agents of issues that may arise in dealing with
the application and where possible suggesting solutions.
|
|
|
|
|
|
|
|
|
|