APPLICATION NO.
|
21/02635/FULLS
|
|
|
|
APPLICATION TYPE
|
FULL APPLICATION - SOUTH
|
|
|
|
REGISTERED
|
08.09.2021
|
|
|
|
APPLICANT
|
LandQuest UK
(Southern) Ltd
|
|
|
|
SITE
|
Oxlease House, Cupernham Lane, Romsey, SO51 7LE, ROMSEY EXTRA
|
|
|
|
PROPOSAL
|
Erection of 35 dwellings with associated parking
and use of the vehicular ingress and egress onto Cupernham Lane following the demolition of the
existing dwelling and other outbuildings.
|
|
|
|
AMENDMENTS
|
17.11.21 (Drainage, Ecology), 23.02.22
(Trees), 03.03.22 (Drainage), 21.04.22 (Trees), (Landscape &
Ecology) & 27.06.22 (Nitrates)
|
|
|
|
CASE OFFICER
|
Paul Goodman
|
|
|
Delegate to Head of Planning & Building
to:
- Allow
completion of satisfactory consultation with Local Lead Flood
Authority and Natural England
-
Impose any reasonable additional or amended
conditions considered necessary following that process, to
adequately deal with drainage, then
-
Secure a legal agreement to
require;
- Removal
of nitrate mitigation land from agricultural
production
- Future
management of the nitrate mitigation land.
- Nitrate
mitigation monitoring fee
- Future
management of landscaped and biodiversity enhancement areas outside
of residential garden areas.
- New
Forest SPA contribution.
- Offsite
affordable housing contribution.
- s106
monitoring fee
Then PERMISSION
subject to:
|
1.
|
The development
hereby permitted shall be begun within three years from the date of
this permission.
Reason: To comply with the provision of Section 91 of the
Town and Country Planning Act 1990 as amended by Section 51 of the
Planning and Compulsory Purchase Act 2004.
|
2.
|
No development shall
take place above DPC level of the development hereby permitted
until samples and details of the materials to be used in the
construction of all external surfaces hereby permitted have been
submitted to and approved in writing by the Local Planning
Authority. Development shall be carried out in accordance with the
approved details.
Reason: To ensure the development has a satisfactory
external appearance in the interest of visual amenities in
accordance with Test Valley Borough Revised Local Plan (2016)
Policy E1.
|
3.
|
The development
hereby approved shall be undertaken in full accordance with the
provisions set out within the eco urban Arboricultural Implications Assessment and Method
Statement ref 201311 - AIA (17 August 2021), amended Tree Details
Plan ref 190076 32 A and additional Eco 7 Tree Protection Plan
received 12th April 2022.
Reason: To ensure
the enhancement of the development by the retention of existing
trees and natural features during the construction phase in
accordance with Test Valley Borough Revised Local Plan policy
E2.
|
4.
|
Tree protective
measures installed (in accordance with the tree protection
condition 3) shall be maintained and retained for the full duration
of works or until such time as agreed in writing with the Local
Planning Authority. No activities, nor material storage, nor
placement of site huts or other equipment what-so-ever shall take
place within the barrier.
Reason: To ensure
the avoidance of damage to existing trees and natural features
during the construction phase in accordance with Test Valley
Borough Revised Local Plan policy E2.
|
5.
|
All service routes,
drain runs, soakaways or excavations in connection with the
development hereby permitted shall remain wholly outside the tree
protective barrier.
Reason: To ensure
the avoidance of damage to existing trees and natural features
during the construction phase in accordance with Test Valley
Borough Revised Local Plan policy E2.
|
6.
|
No development shall
take place above DPC level until full details of hard and soft
landscape works have been submitted and approved. Details shall
include-where appropriate: proposed finished levels or contours;
means of enclosure; car parking layouts; other vehicle and
pedestrian access and circulation areas; hard surfacing materials;
minor artefacts and structures. Soft landscape works shall include:
planting plans; written specifications (including cultivation and
other operations associated with plant and grass establishment);
schedules of plants, noting species, plant sizes and proposed
numbers/densities. The soft landscape proposals shall include
details of soft boundary treatments to the outside edges of the
site. The landscape works shall be
carried out in accordance with the implementation programme and in
accordance with the management plan.
Reason: To improve the appearance of the site and enhance
the character of the development in the interest of visual amenity
and contribute to the character of the local area in accordance
with Test Valley Borough Revised Local Plan (2016) Policy E1 and
E2.
|
7.
|
No development shall
take place above DPC level of the development hereby permitted
until a schedule of landscape implementation and maintenance for a
minimum period of 5 years has been submitted to and approved in
writing by the Local Planning Authority. The schedule shall include
details of the arrangements for the phasing of the implementation
and ongoing maintenance during that period in accordance with
appropriate British Standards or other recognised codes of
practise. Development shall be carried out in accordance with the
approved schedule.
Reason: To ensure
the provision, establishment and maintenance to a suitable standard
of the approved landscape designs to create and maintain the
appearance of the site and enhance the character of the development
in the interest of visual amenity and to contribute to the
character of the local area in accordance with Test Valley Borough
Revised Local Plan (2016) Policy E1 and E2.
|
8.
|
The development
shall not be occupied until space has been laid out and provided
for the parking and manoeuvring of vehicles to enable them to enter
and leave the site in a forward gear in accordance with the
approved plan and this space shall thereafter be reserved for such
purposes at all times.
Reason: In the
interests of highway safety in accordance with Test Valley Borough
Revised Local Plan (2016) Policy T1.
|
9.
|
Any gates shall be
set back at least 4.5 metres from the edge of the carriageway of
the adjoining highway.
Reason: In the
interest of highway safety in accordance with Test Valley Borough
Revised Local Plan (2016) Policy T1.
|
10.
|
There shall be no
construction or demolition works, no machinery shall be operated,
no processes carried out and no deliveries received or dispatched
outside the following times: 07:30 to 18:00 hours Monday to Friday
and 08:00 to 13:00 hours on Saturday.
In addition, no such activities shall take place on Sundays, Bank
or Public holidays.
Reason: In the
interests of the amenities of neighbouring properties in accordance
with Test Valley Borough Local Plan policies E8 and LWH4.
|
11.
|
No development shall
take place unless or until a Construction Environmental Management
Plan has been submitted to, and approved in writing by, the Local
Planning Authority. The Construction
Environmental Management Plan shall cover the control of noise,
dust and spoil during the demolition, site preparation and
construction phases of development. The Environmental Management
Plan shall include the provision of wheel washing, and any other
suitable facility, to avoid the deposit of spoil onto the highway
network. Work shall be undertaken in accordance with the approved
Environmental Management Plan.
Reason: In the
interests of the amenities of neighbouring properties in accordance
with Test Valley Borough Local Plan policies E8 and LWH4.
|
12.
|
Before the
development hereby permitted is commenced details, including plans
and cross sections, shall be submitted to and approved by the Local
Planning Authority of the existing and proposed ground levels of
the development and the boundaries of the site and the height of
the ground floor slab and damp proof course in relation thereto.
Development shall be undertaken in accordance with the approved
details.
Reason: To ensure satisfactory relationship between the
new development and the adjacent residential dwellings, and amenity
areas in accordance with Test Valley Borough Revised Local Plan
(2016) Policy E1 and LHW4.
|
13.
|
The development
hereby approved shall be designed and built to meet Regulation 36 2
(b) requirement of 110 litres/person/day water efficiency set out
in part G2 of Building Regulations 2015.
Reason: In the
interests of improving water usage efficiency in accordance with
policy E7 of the Test Valley Borough Revised Local Plan 2016.
|
14.
|
Prior to the
commencement of development full details of the layout for the
parking and manoeuvring onsite of contractor's and delivery
vehicles during the construction period shall be submitted to and
approved in writing by the Local Planning Authority. The approved
scheme shall be implemented prior to the commencement of
development and retained for the duration of the construction
period.
Reason: In the
interest of highway safety in accordance with Test Valley Borough
Local Plan 2016 policy T1.
|
15.
|
Development shall
proceed in accordance with the measures set out in the Bat Surveys
& Mitigation Strategy (Ecosupport,
November 2021), the Biodiversity Enhancement & Mitigation
Strategy (Ecosupport, April 2022), the
Preliminary Ecological Appraisal (Ecosupport, November 2021) and the GCN Mitigation
Strategy (Ecosupport 2021), unless
varied by a European Protected Species (EPS) license issued by
Natural England. Thereafter, the mitigation and enhancement
measures shall be permanently maintained and retained in accordance
with the approved details. The results of the compliance checks,
outlined within Section of the report shall be submitted to the
local planning authority within 6 months of completion.
Reason: to ensure
the favourable conservation status of protected species in
accordance with Policy E5 of the Test Valley Revised Local Plan
DPD.
|
16.
|
Prior to
commencement, an Environmental Management Plan (EMP), incorporating
measures to avoid impacts on protected species and retained
habitats during construction works shall be submitted to and
approved in writing by the Local Planning Authority. Development
shall subsequently proceed in accordance with any such approved
details.
Reason: To protect
notable locally designated sites in accordance with Policy E5 of
the Revised Test Valley Local Plan DPD.
|
17.
|
Prior to
commencement, a long term ecological management strategy, covering
a period of at least 10 years, as well as a detailed planting
scheme to be incorporated into the development shall be submitted
to and approved in writing by the Local Planning Authority.
Development shall subsequently proceed in accordance with any such
approved details, with photographic evidence provided to the Local
Planning Authority within 6 months of occupation.
Reason: To enhance
biodiversity in accordance with NPPF and the Natural Environment
and Rural Communities Act 2006 and with Policy E5 of the Test
Valley Revised Local Plan DPD 2011-2029.
|
18.
|
The development hereby permitted shall not be carried
out except in complete accordance with the details shown on the
submitted plans, numbers:
5572 / 208
1611 L90-200 G
190076 01
190076 02 A
190076 03 B
190076 05
190076 06
190076 07
190076 08
190076 09
190076 10
190076 11
190076 12
190076 13
190076 14
190076 15
190076 16
190076 17
190076 18
190076 19
190076 20
190076 21
190076 22
190076 23
190076 24
190076 25
190076 26
190076 27
190076 28
190076 30 B
190076 31
Reason: For the avoidance of doubt and in the interests