Venue: Conference Room 1, Beech Hurst, Weyhill Road, Andover
Contact: Sally Prior - 01264 368024
Email: sprior@testvalley.gov.uk
Items
No. |
Item |
345. |
Public Participation
Minutes:
Councillor Coole
made representation on application
19/02397/VARN.
|
346. |
Minutes
Minutes:
Resolved:
That
the minutes of the meeting held on 2 January 2020 be confirmed and
signed as a correct record.
|
347. |
Schedule of Development Applications
Minutes:
Resolved:
That
the applications for development, as set out below, be determined
as indicated.
|
348. |
19/02397/VARN PDF 429 KB
(OFFICER RECOMMENDATION: PERMISSION)
SITE: Abbotts Ann Solar Park
Photovoltaic Installation, Dipden Bottom Lane, Goodworth Clatford,
GOODWORTH CLATFORD
CASE OFFICER: Ms Katherine
Bundy
Additional documents:
Minutes:
|
APPLICATION NO.
|
19/02397/VARN
|
|
APPLICATION TYPE
|
VARIATION OF CONDITIONS - NORTH
|
|
REGISTERED
|
04.10.2019
|
|
APPLICANT
|
Abbotts Ann Farm Solar Park Limited
|
|
SITE
|
Abbotts Ann Solar Park Photovoltaic
Installation, Dipden Bottom Lane,
Goodworth Clatford, GOODWORTH CLATFORD
|
|
PROPOSAL
|
To
vary condition 1 (time limit) of 14/02110/FULLN (Proposed solar
park comprising the erection of solar arrays, inverters,
transformers, equipment housing, security fencing and ancillary
equipment) to extend the length of planning permission to 40 years
from the first export date (28/03/2015)
|
|
AMENDMENTS
|
18.12.2019 – Further justification for
application received.
|
|
CASE OFFICER
|
Katherine Bundy
|
|
|
|
PERMISSION subject
to the following conditions, notes and the prior completion of a
Deed of Variation to the section 106 agreement secured under
planning permission reference 14/02110/FULLN to secure traffic
routing.
|
|
|
1.
|
This permission
shall be for a period of 40 years from the date that the
development is first connected to the grid (the "First Export
Date").
The development
shall be removed and the land restored to its former condition no
later than the date 40 years from the First Export Date
(28/03/2015) or within six months of the development failing to
generate electricity for 12 consecutive months, whichever occurs
first. All structures and materials, and any associated goods and
chattels shall be removed from the site and the land shall be
restored to its former condition in accordance with a scheme of
decommissioning work and land restoration that shall have first
been submitted to and approved in writing by the Local Planning
Authority.
Reason: In order that the land is restored to its
original condition following the expiry of the period of time
whereby electricity is likely to be generated by the proposed
development and for which a countryside location has been shown to
be essentially required, in accordance with policies COM2 and E2 of
the Test Valley Borough Revised Local Plan 2016.
|
|
|
2.
|
The development
hereby approved shall be carried out in accordance with the drawing
numbers listed on the decision notice issued for application
reference 14/02110/FULLN: 2605_4, 2605_5, 2664_6, 2664_7, 2664_8,
1214-0201-29, 1214-0200-05, 1214-0204-00 Rev. 02, 1214-0201-27,
1214-0500-01 and 2664-100 F.
Reason: For the avoidance of doubt and in the interest of
proper planning.
|
|
|
3.
|
The external
surfaces of the DNO Switchgear, private switchgear and fence shall
be maintained and retained in Moss Green (RAL: 6005) and the
external surfaces of the spares container shall be maintained and
retained in Bottle Green (RAL: 6007), in accordance with the
approved details.
Reason: To ensure the development has a satisfactory
external appearance in the interest of visual amenity in accordance
with Test Valley Borough Revised Local Plan 2016 policy E1.
|
|
|
|
|
|
|
|
|
4.
|
The development
shall be managed in accordance with the approved landscape
management plan, titled ‘Landscape & Landscape Management
Plan,’ Rev D, and dated 24.03.2015, and any subsequent
amendments to the landscape management regime as have first been
agreed in writing by the Local Planning Authority as part of the
approved review process.
Reason: To improve the appearance of the site and enhance
the character of the development, and ... view
the full minutes text for item 348.
|
|