No. |
Item |
226. |
Public Participation
Minutes:
In accordance with the
Council’s scheme of Public Participation, the following spoke
on the applications indicated:
Agenda Item No.
|
Page No.
|
Application
|
Speaker
|
7
|
10 -
23
|
20/01106/VARN
|
Miss Jones
(Applicant)
|
|
227. |
Minutes
Minutes:
Resolved:
That
the minutes of the meeting held on 30 July 2020 be confirmed and
signed as a correct record.
|
228. |
Schedule of Development Applications
Minutes:
Resolved:
That
the applications for development as set out below be determined as
indicated.
|
229. |
20/01106/VARN PDF 431 KB
(OFFICER RECOMMENDATION: PERMISSION)
SITE: Solar Array, Lains Farm,
Cholderton Road, AMPORT
CASE OFFICER: Mr Luke Benjamin
Additional documents:
Minutes:
|
APPLICATION NO.
|
20/01106/VARN
|
|
APPLICATION TYPE
|
VARIATION OF CONDITIONS
- NORTH
|
|
REGISTERED
|
26.05.2020
|
|
APPLICANT
|
Lightsource BP
|
|
SITE
|
Solar Array,
Lains Farm, Cholderton Road, AMPORT
|
|
PROPOSAL
|
Variation of Condition 1 (Time
limit) of Planning Permission 17/02481/VARN - (Installation of 5MW
ground mounted photovoltaic solar arrays with transformer stations;
internal access track; biodiversity enhancement; landscaping; stock
fencing; security measures; access gate; and ancillary
infrastructure)
|
|
AMENDMENTS
|
Supporting information –
24.06.2020
|
|
CASE
OFFICER
|
Mr Luke Benjamin
|
|
|
|
PERMISSION subject to the following conditions, notes and the
prior completion of a Deed of Variation to the section 106
agreement secured under planning permission reference 17/02481/VARN
to secure traffic routing:
|
|
|
1.
|
This
permission shall be for a period of 40 years from the date that the
development is first connected to the grid (the "First Export
Date").
The development shall be
removed and the land restored to its former condition no later than
the date 40 years from the First Export Date (24.03.2016) or within six months
of the development failing to generate electricity for 12
consecutive months, whichever occurs first. All structures and
materials, and any associated goods and chattels shall be removed
from the site and the land shall be restored to its former
condition in accordance with a scheme of decommissioning work and
land restoration that shall have first been submitted to and
approved in writing by the Local Planning Authority.
Reason: In order that the land is
restored to its original condition following the expiry of the
period of time whereby electricity is likely to be generated by the
proposed development and for which a countryside location has been
shown to be essentially required, in accordance with policies COM2
and E2 of the Test Valley Borough Revised Local Plan
2016.
|
|
|
2.
|
The
development hereby permitted shall not be carried out except in
complete accordance with the details shown on the submitted plans,
numbers SK02B, COMPOUND, BRS.5141_11-C, V10, PV-0154-01, SOL-023,
SOL-55 Rev D01, SOL-56 Rev D01, SOL-57 Rev D01 PV-0154-02 V5,
PV-0154-03 V8, PV-0154-04 V3, PV-0154-04 V9, PV-0154-06
V2
Reason: For the avoidance of doubt
and in the interest of proper planning.
|
|
|
3.
|
The
external surfaces of the substation and inverter station structures
shall be finished in a matt dark green finish. The structures shall
thereafter be maintained and retained in this colour.
Reason: To ensure the development
has a satisfactory external appearance in the interest of visual
amenity in accordance with Test Valley Borough Revised Local Plan
2016 policy E1.
|
|
|
4.
|
No
tree or hedge within and adjacent to the boundary of the
application site shall be removed other than those identified on
drawing number BRS.5141_17-B submitted as part of the Arboricultural Survey, Impact Assessment and Tree
Protection Plan by TechArborA dated 4th
February 2015 and on drawing SK02 B.
All other trees and hedges within and adjacent to the boundary of
the application site shall be retained for the duration of the
planning permission or until the site is decommissioned, whichever
is the sooner.
Reason: To safeguard the existing
trees ... view